MILESTONES IN BUILDING CONSTRUCTION AS OF JULY 2007
July. 07, 2006: Obtained Building Permit.
July. 17, 2006: Building construction started with survey & stakeout, tree
cutting and clearing the construction area.
July. 22, 2006: Completed land clearing for the building, removed topsoil
and installed silt fence.
Aug. 03, 2006: Started excavation of basement and building pad.
Aug. 08, 2006: Completed excavation of basement and building pad.
Sep. 14, 2006: Concrete poured for footings and foundations.
Oct. 01, 2006: Neighbor provided RV with electricity and gas to be used as
field office.
Oct. 03, 2006: Concrete poured for north wall and parts of east and west
walls.
Oct. 07, 2006: Plumbing work under basement slab started.
Oct. 16, 2006: Concrete poured to complete parts of east and west walls.
Nov. 7, 2006: Concrete poured for south wall completing the basement.
Nov. 19, 2006: Concrete poured for floor of basement.
Dec. 11, 2006: Steel erection started.
Jan.12, 2007: Steel erection completed.
Jan.23, 2007: Basement ceiling poured.
Feb.02, 2007: Staircases to basement installed.
Feb.21, 2007: Water pipes installation started.
Jun.08, 2007: Concrete poured for ramp and step footing.
Jun.29, 2007: Concrete poured for side walls of ramp and steps.